Hi zillains
Give Answer and rating at this question:
Which one of the following is correct statement for BAC?
A.Total PV for a project is known as BAC
B.Total EV for a project is known as BAC
C.AC plus remaining funding value is known as BAC
D.An estimated value during any stage of project is known as BAC.
Cheers
Forums:


aliweb
Mon, 07/09/2012 - 16:01
Permalink
Please define what PV, EV and
Please define what PV, EV and AC are.
krantikumar50
Mon, 07/09/2012 - 17:10
Permalink
It stands for...
Hi Aliweb,
PV= Planned Value
EV= Earned Value
AC= Actual Cost
Do not bother much about the abbreviations. In the exam all will be spelled out.
Warmly, KK
diba_perfect
Mon, 07/09/2012 - 16:11
Permalink
The answer should be "A".
The answer should be "A". (Though technically even option "C" isn't incorrect).
Pawarji plz confirm.
~ Diba
Zephyr
Mon, 07/09/2012 - 16:54
Permalink
Answer is 'A'
Answer is 'A'
sspawar
Mon, 07/09/2012 - 17:46
Permalink
YES A is correct
Refer 5th line of p 182
others are some thing different compare wth Definition of BAC p 428
EV for a project = BCWP
AC plus remaining funding value = AC+(BAC-AC) or AC+(EAC-AC), partially correct as DIBA answered partially.
An estimated value during any stage of project is known as = AC+ETC.
this q is framed by me.
Regards
krantikumar50
Mon, 07/09/2012 - 21:03
Permalink
By you????
Wow!!! Such a masterpiece creation respected Pawarji Sir.
I feel we should have guessed that such masterpiece can come only from a legend like respected Pawarji Sir.
Classic piece Sir.
I am amazed. No wonder that I say that such certifications are infradignitatem for a legend like respected Pawarji Sir.
Bravo respected Pawarji Sir!!!
Warmly, KK....