BAC

Hi zillains
Give Answer and rating at this question:

Which one of the following is correct statement for BAC?
A.Total PV for a project is known as BAC
B.Total EV for a project is known as BAC
C.AC plus remaining funding value is known as BAC
D.An estimated value during any stage of project is known as BAC.

Cheers

Please define what PV, EV and AC are.

Hi Aliweb,


 


PV= Planned Value


EV= Earned Value


AC= Actual Cost


 


Do not bother much about the abbreviations. In the exam all will be spelled out.


 


Warmly, KK

The answer should be "A". (Though technically even option "C" isn't incorrect).

 

Pawarji plz confirm.

 

 

~ Diba

 Answer is 'A'

Refer 5th line of p 182

others are some thing different compare wth Definition of BAC p 428

EV for a project  = BCWP
 

AC plus remaining funding value = AC+(BAC-AC) or AC+(EAC-AC), partially correct as DIBA answered partially.
 

An estimated value during any stage of project is known as = AC+ETC.

this q is framed by me.

Regards

Wow!!! Such a masterpiece creation respected Pawarji Sir.


 


I feel we should have guessed that such masterpiece can come only from a legend like respected Pawarji Sir.


 


Classic piece Sir.


 


I am amazed. No wonder that I say that such certifications are infradignitatem for a legend like respected Pawarji Sir.


 


Bravo respected Pawarji Sir!!!


 


Warmly, KK....