Question 108 from Oliver Lehmann 175Qs
108. Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000, EV: $1,000,000, AC: $1,200,000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC – EV) is at $1,000,000, what should be your new EAC (estimate at completion)?
o $1,800,000
o $2,000,000
o $2,200,000
o $2,400,000
Answer says to use "EAC forecast for ETC work considering both SPI and CPI factors", i.e. AC + [(BAC-EV)/CPI*SPI]. Why? The question's scenario seems not to meet the application condiction of the formula. I think the other formula is more suitable: AC + [(BAD-EV)/CPI]. Do you thinks so?


sspawar
Thu, 06/07/2012 - 12:52
Permalink
Yes , It is like that
EAC = AC + ETC
CPI at current point = EV/AC = 1000000/1200000
Trend will be same in future
ETC = Remaining work (BAC- EV) / CPI = 1000000/1000000/1200000 = 1200000
EAC = AC+ETC = 1200000+1200000 = 2400000, ans would be D
sspawar
Fri, 06/08/2012 - 00:27
Permalink
Why *****/CPI*SPI will not here
When Planned deadline is a constraint or condition to complete project, and in any point of time , project is running ahead or behind with any SPI, along with any CPI, then in that case, you apply this formula for EAC :
EAC = AC + [(BAC-EV)/(SPI*CPI)]
But in question it not asked to complete at scheduled date.
hence formula will be applied only with CPI.
Regards
danny2012
Fri, 06/08/2012 - 10:30
Permalink
yes, it didn't mention
yes, it didn't mention schedule factor. That's why I'm confused by the explanation of it. Thanks anyway.