Required: Answers with explanation
Can someone provide the answers with explanations to the following questions in the Quality Management
You are setting up a factory making nails and the quality plan specifies the pro
cess will adhere to 3 sigma standards. While inspecting the first lot of 500,000
, there were 1000 defective pieces. Are you meeting the quality goals and how ma
ny defective pieces you can have for a lot of 500,000 if you are at 6 sigma?
You are with in quality goals now and you can have 50 defective pieces when yo
u are 6 sigma
You are with in quality goals now and at six sigma you can have only 300 defec
t pieces
You are not with in quality goals now and at 6 sigma you can have 1350 defecti
ve pieces
You are not with in quality goals and you can have 300 defective pieces at 6 s
igma
For an activity, the optimistic, most likely and pessimistic estimates are 12, 1
6 and 18 respectively. Which of the following statement is correct?
There is 68.26% chance that the activity will be completed in 15 to 17 days
There is 95.44% chance that the activity will be completed in 15 to 17 days
There is 68.26% chance that the activity will be completed in 14.67 to 16.67 d
ays
There is 93.73% chance that the activity will be completed in 15 to 17 days
If the optimistic estimate for an activity is 18 and standard deviation is 3. If
the Most likely estimate is 30, the chance the activity will be finished betwee
n 23 and 35 days is
95.44
68.26
99.73
99.999


trawal
Thu, 05/17/2012 - 13:16
Permalink
My answers below 1) A 2) C 3)
My answers below
1) A
2) C
3) C (I think we are missing pessimistic days estimation in this question but if not then I would guess B as 3 std deviation can give you 12 day range)
karthik21
Thu, 05/17/2012 - 16:20
Permalink
Thanks... can you please
Thanks... can you please provide an explataion for the selections?
ameenhaqqi
Thu, 05/17/2012 - 17:09
Permalink
Q1: ANS (A)1000/500,000 =
Q1: ANS (A)
1000/500,000 = 0.002 or 0.2% defects per unit, it seems like within a quality goal beacuse 3 sigma is 99.73%
Six sigma is 99.99% it should be close to 50 i believe. Therefore answer is A. (Not sure the answer and calculation though).
Q2: ANS (C)
By utilizing PERT and standard deviaition formulas P+4*MP+O/6 and P-O/6 , we can calculate the following
PERT Calc = 15.667 or 15.67 and SD = 1 or +/- 1, therefore option c should be correct.
Q3: ANS (A)
Range: 23days - 35 days = 12 days (mean value = 29days)
Pessimistic value is missing here but based on given st, dev. SD=3 at 68.26% means +3 to -3 days
therefore range = 6 or we can say 26 - 32 days with one standard dev,
hence for two stand. deviation sd = 3x 2 = 6 or +/- 6 range
so, there is a 95.44% chance that activity will be finished between the 23days - 35days, the answer should be "A" not "C" - calculated based on the value 3 for SD.
sspawar
Sun, 05/20/2012 - 16:30
Permalink
Question 1 is manipulated
Dear Mr. Karthik
This question is manipulated,
As per Normal distribution and 6 sigma theory - this question can be answered like this-
3sigma - accuracy required - 99.73% and for 500000 samples defective pieces should not be more than 0.27% =1350.
Hence if 1000 defective pieces are there, then process is meeting to the 3 sigma accuracy.
6sigma - acuracy required - 99.9996% and for 1million not more than 3.4defects are be there. (0.00034%) hence for 500,000 defects should not be more than = 1.7~ 2. Means not more than 2 pieces should be defective to meet 6sigma accuracy.
when we go for options - all are vague.
2. Question 2, is ok answer is C, the mean value will (12+4x16+18)/6 = 15.7, and sd =(18-12)/6 = 1
hence for 1sigma = 68.26 % chance are there for 14.7 to 16.7 days is correct.
Here little confusion may arise with = most likely or realstic chance of duration is 16 days may be considered as mean(myu). But mean value after calculation by 3 point formula is correct. Most likely value is raw data.
3.
let see:
OP = 18
SD = 3
Most likely is 30
what is chance of 23 to 35 days
now SD =( ps-op)/6 = (ps -18)/6 = 3
hence ps = 36days
Now mean (expected duration) value is = (18+4x30+36)/6 = 29days
from this value - 23 days have -6 days variance,
while 35 days have +6days variance
It ranges between - 6/3 = - 2sigma to +6/3 = 2sigma
as per this information answer would be = 95.44%- Option A
----------------------------------------------------------------------
Friends,
I like this forum, but I could come very rare here, because of my busy schedule.
Regards
karthik21
Mon, 05/21/2012 - 06:50
Permalink
Thank you very much for the
Thank you very much for the explamnation. ITs clear now