Payback and NPV

  Question

There are 3 projects to be chosen from with following data

Project A             Project B              Project C

NPV                                       40000                    50000                    75000

Payback Period                 6month                                3month                                12month

Which option/project will be the best?

A project A

B project B

C project C

D Data are insufficient

The project with the highest NPV is taken. The other infos are simple pile-on... Thanks, KK....

I think, highest NPV should be taken.

GOOD GOOD

Excellent post. I want to thank you for this informative read, I really appreciate sharing this great post. Keep up your work. Thanks for this very useful info you have provided us.650-195//642-427//640-721//642-647//646-205//642-457//642-661//642-165//646-364//640-864//642-627//642-447//642-874//JK0-016//N10-004//SY0-201//vmware certification//cissp//photoshop certification//sas certification//ibm certification//symantec certification//CCNP//SY0-301