Float question from time management

The earliest Task C can finish is January 21, and the earliest the next task can start is January 28. From this information we can be sure that:


A.  Task C has 6 days of float
B.  Task C has 6 days of free float
C.  Task C has 7 days of free float
D.  Task C has 7 days of float

 

Please also briefly explain the choice.

Thank you all.

Free Float is the amount of time activity (C) can be delayed without delaying the early start date of next task.

or Free Float= Early start date of successor activity- Early start date of precessedor activity

Free Float= 28-21=7.

You can follow the below link for more details regarding free float

http://www.deepfriedbrainpmp.com/2009/08/total-free-float-cpm-network-diagram.html

 

 

Float of 'C' = Earliest start of Subsequent task-Earliest Finish of C - 1

               = 28-21-1= 6 days

By Jan. 27, C must be finished so next Activity 'D' can start on Jan. 28.    Even if you look at : Float = LF-EF= 27-21=6 days is the maximum relaxing period you get.

Another way to look at is: You can finish as early as Jan. 21.  So Jan 22, 23, 24, 25, 26, 27 ( 6 days) are your spare days without causing delay to start the next activity on Jan. 28.

 

Chandra

Chandra, Your answer is right.

 

Even i made a mistake picking 7 days of free float.

6 Days free float is right.

 

Thank you for the explanation.