Rita EVM Exercise Fence #2

Hi All,

Would like to receive some help on the EVM exercise on Page 273.
In this exercise,the trend is not constant but yet EAC formula used is BAC/CPI.

Can anyone explain??

Could you pls post the question here ?

is it PMBOK5 or RITA?

i got in RITA e-version pdf page no 287 Exercise fence#2.

The question is stupidity.
They said Finish to Finish Relationship.
The question is totally confusing.

Actually they need to mention Fast TRack instead of F-2-F.