Rita EVM Exercise Fence #2
Submitted by chullan88 on Sat, 05/31/2014 - 09:51
Hi All,
Would like to receive some help on the EVM exercise on Page 273.
In this exercise,the trend is not constant but yet EAC formula used is BAC/CPI.
Can anyone explain??
Forums:


sanjay077
Mon, 06/02/2014 - 16:35
Permalink
hi
Could you pls post the question here ?
sunku65
Tue, 06/03/2014 - 14:33
Permalink
is it PMBOK5 or RITA?
is it PMBOK5 or RITA?
sunku65
Tue, 06/03/2014 - 14:44
Permalink
i got in RITA e-version pdf
i got in RITA e-version pdf page no 287 Exercise fence#2.
The question is stupidity.
They said Finish to Finish Relationship.
The question is totally confusing.
Actually they need to mention Fast TRack instead of F-2-F.