Question related to Close Process - PMP - Correct order of action
Submitted by hemald on Thu, 08/20/2015 - 04:25
Which of the following is the correct order of actions that you take during the closing processes?
1) Get formal acceptance, release the team, write lessons learned, close the contract
2) Write lessons learned, release the team, get formal acceptance, close the contract
3) Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract
4) Get formal acceptance, close the contract, write lessons learned, release the team
Please let me know the correct answer.
Forums:


vishwanathkanchipmp
Thu, 08/20/2015 - 06:01
Permalink
4
4
hemald
Thu, 08/20/2015 - 13:48
Permalink
Thanks - But test site mentions 3
Thanks for this information.
Test Site mentions the answer as 3.
Therefore, I was confused.
Thanks
admin
Mon, 08/24/2015 - 05:08
Permalink
This is a tricky question ,
This is a tricky question , so its important to understand the closing process as a whole.
There is ambiguity in the question because the "Close contract" can be close procurement contract or closing the final project contract with client. Depending upon what you assume the answer can vary.
I would go with option 4 as it seems more safe for PMP
hemant_acs
Tue, 08/25/2015 - 12:44
Permalink
correct answer is 3
1 is wrong as the team can not release before write lesson learned. 2 is wrong as the team can not release before formal acceptance. third is correct. 4 is wrong as write lession learned done before close the contract