You are one of the ten full-time project managers in your organization. All of you share two administrative resources. Normally, around 30 - 40 projects are executed per year involving about 30% of the employees of the organization. However, all of them do not report to you, although you are their project manager. Your organization can best be classified as:
Choice 1 Projectized
Choice 2 Balanced Matrix
Choice 3 Strong Matrix
Choice 4 Weak Matrix
Forums:


Jgrind07
Wed, 05/15/2013 - 04:03
Permalink
Choice 2 Balanced Matrix
Choice 2 Balanced Matrix
motivation
Wed, 05/15/2013 - 05:03
Permalink
Choice 3
Choice 3 ---Strong Matrix
rwmv
Wed, 05/15/2013 - 06:03
Permalink
Choice 3
Choice 3 Strong Matrix
pmpnewster
Wed, 05/15/2013 - 11:57
Permalink
2. Balanced Matrix
2. Balanced Matrix
1. Ruled out, since only about 30% of employees are involved in projects.
3. Ruled out, since some of the project manager's own team members do not report to him/her.
4. Ruled out, since some of the project manager's team members DO report to him/her; i.e. the PM's power is more that that of a mere expeditor/co-ordinator.
I hope I am right!
crushPMP
Wed, 05/15/2013 - 13:02
Permalink
perfect. Correct ans is 2
perfect. Correct ans is 2
azami
Tue, 07/16/2013 - 06:41
Permalink
"Balanced Matrix" because in
"Balanced Matrix" because in every particular organizations much better to have equal all those things.