Question on Scope
Submitted by philzs on Sun, 03/01/2015 - 19:49
From Head First,
Question 105
Which is best description of project scope ?
A ) All of the features and deliverables your project will deliver
B ) All of the products your project will make
C ) All of the people involved in your project
D ) All of the work you will do to build the product
I want to know what do you guys think is the answer and why
thanks
Forums:


coolpmp69
Sun, 03/01/2015 - 20:46
Permalink
the correct answer is option
the correct answer is option A as scope includes all the work and only work that project will deliver.
Option B - product scope
pmpstudent121
Mon, 03/02/2015 - 09:14
Permalink
Ans D
Answer should be D - all work needed to build the product.
coolpmp69
Mon, 03/02/2015 - 14:28
Permalink
@ pmpstudent121 : Option D is
@ pmpstudent121 : Option D is product requirements not project scope.
philzs
Mon, 03/02/2015 - 21:10
Permalink
Answer from Head first is (
Answer from Head first is ( which i think they are wrong )
Answer: D
Product scope means the features and functions of the product or service being built. Project
scope means the work that’s needed to build the product.
philzs
Mon, 03/02/2015 - 21:11
Permalink
I think pmstudent121 is right
I think pmstudent121 is right, answer D should be wrong, it look like requirement
SumathiCH
Tue, 03/03/2015 - 19:14
Permalink
D is correct.
All work to produce features or products or components agreed to be delivered is project scope.