Need help with a question: Why it is called early termination of project
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?
o The project was terminated early. At that time, it was over budget and ahead of schedule.
o The project has produced additional deliverables which were originally not required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.
The answer is 1 How do we know that project was terminated earlier and not been finished.
Thanks
admin
Wed, 03/04/2015 - 09:28
Permalink
Already discussed
Already discussed
http://pmzilla.com/project-terminated-vs-closed
You can search on PMZilla.
coolpmp69
Wed, 03/04/2015 - 14:22
Permalink
post mortem implies that
post mortem implies that something you want to investiagte about. So here you are trying to investiage the reason for early closure/termination of the project. CPI and SPI does not add any valuse excepting providing status at the time of project closure.