Develop team question.

cnppmp's picture

q1) A new team member gets assigned to project . The project manager subsequently discovers the team member does not have adequate tech nical knowledge for project


whcih of the following represnets BEST answer:


1. Ask a fellow etam member to provide training to the new team member


2. Ignore the issue


3. Arrange to provide training to the new team memeber frm project contingency funds


4. Ask the client to arrange for trainings


 


Regards


CN Patil

 option 3???

2 is wrong as you can ignore issue

3 is becuase contingency fund is for identified / Known risks

4 can ask client to bear the cost

So only option left is 1

jvleminc's picture

I agree with 1. 

 Ask a fellow team member to provide training to the new team member

On the Job training from another project team member is a recognized way of training method given in pmbok 232