Develop team question.
Submitted by cnppmp on Mon, 05/20/2013 - 17:23
q1) A new team member gets assigned to project . The project manager subsequently discovers the team member does not have adequate tech nical knowledge for project
whcih of the following represnets BEST answer:
1. Ask a fellow etam member to provide training to the new team member
2. Ignore the issue
3. Arrange to provide training to the new team memeber frm project contingency funds
4. Ask the client to arrange for trainings
Regards
CN Patil
Forums:


vijayavadrevu
Mon, 05/20/2013 - 17:41
Permalink
option 3???
option 3???
sanskrit
Tue, 05/21/2013 - 00:27
Permalink
1 ?
2 is wrong as you can ignore issue
3 is becuase contingency fund is for identified / Known risks
4 can ask client to bear the cost
So only option left is 1
jvleminc
Mon, 05/27/2013 - 20:50
Permalink
I agree with 1.
I agree with 1.
Geethika
Tue, 05/28/2013 - 08:44
Permalink
1
Ask a fellow team member to provide training to the new team member
On the Job training from another project team member is a recognized way of training method given in pmbok 232