Q from pm study


Which of the following should you (the buyer) pay attention to when you Conduct Procurements?
 
 
  Choice 1 Ensure that contractual obligations are met.
 
  Choice 2 Apply appropriate project management processes to the contractual relationship and integrate the outputs from these processes to the overall management of the project.
 
  Choice 3 Monitor payments to the seller.
 
  Choice 4 Perform regular procurement audits.
 

 

admin's picture

Conduct procurements is a process of obtaining seller responses, selecting a seller and awarding a contract.  This rules out choice 1, 3 and 4.