Q from pm study
Submitted by igelles on Mon, 07/20/2015 - 01:54
Which of the following should you (the buyer) pay attention to when you Conduct Procurements? |
||
| Choice 1 | Ensure that contractual obligations are met. | |
| Choice 2 | Apply appropriate project management processes to the contractual relationship and integrate the outputs from these processes to the overall management of the project. | |
| Choice 3 | Monitor payments to the seller. | |
| Choice 4 | Perform regular procurement audits. | |
Forums:


admin
Mon, 07/20/2015 - 03:45
Permalink
Conduct procurements is a
Conduct procurements is a process of obtaining seller responses, selecting a seller and awarding a contract. This rules out choice 1, 3 and 4.