initial phase question

Which of the following is not accurate about the initial phase of a project?

  1. The highest uncertainty is at this stage of the project

  2. The cost associated at the beginning of the project is highest

  3. Stakeholders have maximum influence during this phase

  4. Staffing levels are the highest at this stage

 

I thought both 2 and 4 are correct. Staffing level are the highest at the execution phase,not initial phase. your thoughts? 

admin's picture

Staffing levels are high during the execution phase. 

Cost associated may not be highest in beginning of the project. unless the Question is assuming the unspent cost , which will be highest.

So ya. 2 and 4 both seem correct. 

gomsy's picture

I concur with admin... the answer 4 is  inaccurate  for initial phase...

I agree with you Sinosino. Both 2 and 4 are correct.