changes in the project

You are a project manager for Rupert Technologies. Rupert writes custom CRM applications for several BPOs. A schedule change has been requested. You know change is concerned with all of the following except which one?

A)Determining that a change occurred

B)Influencing causes of change

C)Verifying change

D)Managing change

 

 

 

 

 

 

This could be A. Determining the change is part of scope baseline.

A ? Determining that a change occurred (As Changes has not occured, It's has been requested) So PM's Job is to 

Influencing causes of change

Managing change

Verifying change (Verify the Change Impact)

so how you can manage the change !!!

cnppmp's picture

B?

 I too have answered as A. But C is given as the right answer with the explanation, 

"Integrated Change Control, Schedule Control, and Cost Control are all concerned with three issues: influencing the things that cause change, determining that change is needed or has happened, and managing the change."

Can someone explain the reference to authenticate this?