Question on Tuckman - develop team vs manage team

Tuckman is under develop project team in pmbock

Forming

Storming

Norming

Performing

Adjourning

I got a question that asked Which HR proces requires a varetiy of management skills for fostering teamwork and integrating the offorts team members to create high-performance teams.

I tought the answer would be "Develop Project team" as this is a process and this process carry the "performing" under tuckman

Anyone can give a trick on that kind of question ?

 

The answer was MAnage project team

 

thanks

anyone?

Answer is - C , Coz in norming stage newly accuried team get familiar with co-team mebers and get accumutated with the organizational/project environment.

So As per me the beast management practice required during Norming phase to get the best output from the team.

Pl. correct me if I am wrong.

Rgds,

-Sudeep