Math questions - need explaination
Hi,
I would appreciate of someone elaborate/explain the answers for following questions -
1) A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.The second project would be the development of a new product which could produce the following net profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the first 3 years, what is true?
1) Both projects are equally attractive.
2) The first project is more attractive by app. 7%.
3) The second project is more attractive by app. 5%.
4) The first project is more attractive by app. 3%.
2) You are running a project for a customer based on a cost-reimbursable contract with the following terms:
Target costs: $ 1,000,000
Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000
Which is the PTA (= point of total assumption, break point) of the project?
1) $1,300,000
2) $1,500,000
3) $80,000
4) $1,125,000


harsh.athalye
Mon, 03/09/2015 - 11:23
Permalink
First question requires you
First question requires you to calculate PV for both projects and then find out which one is better.
In case of project 1,
1st year = 120000/(1+0.05)^1 = $ 114286
2nd year = 120000/(1+0.05)^2 = $ 108844
3rd year = 120000/(1+0.05)^3 = $ 103661
Total = $326,791
Project 2
1st year = 15000/(1+0.05)^1 = $ 14286
2nd year = 125000/(1+0.05)^2 = $ 113379
3rd year = 220000/(1+0.05)^3 = $ 190044
amitd
Mon, 03/09/2015 - 16:00
Permalink
Thanks..
Thank you very much !