basic question - work performance info

Work performance information is output of _________

 

1. defice scope

2. perform integrated change control

3. direct and manage project execution

4. minitor and control project work

 

what do you think

3. direct and manage project work 

From pmbok
Work performance information is an output of :
Control Schedule
Control Cost
Perform Quality Control
Control Communications
Monitor and Control Risks
Control Procurements
Control Stakeholder Engagement

How can you say it's from Direct and manage project Work ???

Philzs : Your are right. The correct answer is monitoring and controlling process.   I annswered it thinking assuming work performance data  ...my bad :(

ok no problem.

 

by the way,  Cert Champ says it's part of Executing.

 

Cert Champ is not good at all

There are lot of PMP practice test available online but they are not genuine. So avoid such tests

that one was from a source that many people give good feedback