You are into Schedule development phase of your project. You have been asked to emphasize on resources required to do project tasks, more than task orders or schedules. With this in mind which of the following tools will you use?
Response:
A. Critical Path
B. Resource Leveling
C. Resource Calendars
D. Critical Chain Method
Forums:


YogSam
Mon, 02/02/2015 - 18:07
Permalink
critical chain is resource
critical chain is resource constrained method. check pmbok again.
coolpmp69
Mon, 02/02/2015 - 21:51
Permalink
@YogSam : do you mean " The
@YogSam : do you mean " The resource-constrained critical path is known as the critical chain"?
YogSam
Tue, 02/03/2015 - 00:45
Permalink
Coolpmp69, Its time to read
Coolpmp69, Its time to read PMBOK5 again. Page 178, First Para, last sentence, Thanks.
YogSam
Tue, 02/03/2015 - 00:47
Permalink
Yes. I believe you saw it.
Yes. I believe you saw it. Thats the one i am referring to.
VinC
Wed, 02/04/2015 - 14:45
Permalink
http://pmzilla.com/what
http://pmzilla.com/what-difference-between-resource-levelling-and-critical-chain-method