What is the answer
Submitted by vandana singh on Mon, 07/21/2014 - 05:06
119. Harry has been assigned the flyover construction project and he is in the process of initiating the project. In order to meet the customer's project expectations, based on the business and compliance requirements, which of the following should Harry define FIRST?
High level scope of the project
Project schedule
Project Statement of Work
Product Statement of Work
Explanations:
Forums:


Jagdish Nasit
Mon, 07/21/2014 - 13:27
Permalink
Answer
I believe, A. High Level Scope of the project which comes under Develop Project Charter.
Since he is in initiating process, Project schedule cant be the answer and other 2 are inputs to the initiation process.
sanjay077
Mon, 07/21/2014 - 17:22
Permalink
hi
I guess :
Project Statement of Work...
Frances Tessler
Wed, 08/20/2014 - 20:48
Permalink
What you would do first
Determine the Project SOW which is the primary input to developing the project charter.
ruthkim
Wed, 08/27/2014 - 16:07
Permalink
A. High Level Scope of the Project
First of all, be careful of how you feel it is done in the real world in answering PMP questions :)
As mentioned by others, Project SOW is and input to this process and therefore could not be the answer.