Question
You are the project manager at a construction company. Your company is currently in the process of developing a 500 unit apartment complex.your company has subcontracted all the electrical wiring of the building to xyz electrical. The subcontractors work involved wiring the building for electrical power, as well as cable and internet/ Ethernet wiring. The contractor has just completed the work, and you are in the process of inspecting his work.
However, you ve just discovered that the subcontractor forgot to install Cat5 Ethernet /internet cabling throughout the building. The subcontractor's performance did not meet the contract requirement. Which of the following statement are true?
A. You are in the close procurement process and performed a contract audit to verify the contractors work.
B. you are in the validate scope process, and performed a quality audit of the contractors work.
C. You are in the perform Quality assurance process and performed a quality audit of the contractors work.
D. You are in control communication process and performed a performance review of the contractors work.
Correct answer is C. Can anybody please explain why this is correct answer.


eherrera
Tue, 06/10/2014 - 01:27
Permalink
A. You are in the close
A. You are in the close procurement process and performed a contract audit to verify the contractors work.
The question is related to procurement, but in the close procurement process you don't verify or audit the contractor's work. This process just involves administrative activities (procurement audit).
B. You are in the validate scope process, and performed a quality audit of the contractors work.
In the validate scope process, you verify deliverables that are checked for correctness through the Control Quality process. You don't perform a quality audit here.
D. You are in control communication process and performed a performance review of the contractors work.
In the control communication process, you ensure that the information needs of the project stakeholders are met. You don't perform a performance review here.
Perform Quality Assurance is the process of auditing the quality requirements to ensure that appropriate quality standards and operational definitions are used, so one of the techniques of this process is a quality audit.
Nabs
Wed, 06/11/2014 - 19:33
Permalink
Thank u for ur explanation. I
Thank u for ur explanation. I got it clear.
Nabs
Wed, 06/11/2014 - 19:33
Permalink
Thank u for ur explanation. I
Thank u for ur explanation. I got it clear.
Nabs
Wed, 06/11/2014 - 19:34
Permalink
Thank u for ur explanation. I
Thank u for ur explanation. I got it clear.