Stakeholder Analysis
Submitted by Nabs on Mon, 05/12/2014 - 11:44
When do you perform stakeholder analysis?
A. When managing communications on your project
B. When developing the project charter
C. When creating the project management plan
D. When putting changes through change control
Can anyone tell me please why option A is the correct choice.
i think correct choice should be Option B. Stakeholder analysis is done to identify stakeholder which is performed during project inititation.
Many Thanks.
Forums:


Sundara.damaraj...
Mon, 05/12/2014 - 14:24
Permalink
Stakeholder Analysis
It cannot be "B".
During project charter only stakeholders identified.
Their impact,influence(stakholder analysis) is not part of the charter.
I go with "C", because PM plan talks about 'techniques for communicating among stakeholders'.
One of the technique is 'stakeholder anlysis'.
Note:- Some problem with pmzilla server. hence you see the blank submissions before. Apols for the inconvenience.
admin
Mon, 05/12/2014 - 16:48
Permalink
Creating PM Plan is too broad
Creating PM Plan is too broad an item. Stakeholder analysis is for communications hence , closest is A.
Sundara.damaraj...
Tue, 05/13/2014 - 02:46
Permalink
Creating PM Plan is too broad
Hi,
Will you please explain which process process(In Communication Management) uses "Stakeholder analysis" as a technique?
sunku65
Tue, 05/13/2014 - 06:47
Permalink
This question looks like
This question looks like PMBOK 4th edition.
So, answer is Communication Management.
Nabs
Wed, 05/14/2014 - 11:59
Permalink
will there be difference in
will there be difference in answers if answered from 4th or 5th Ed?
Please give your opinion on this question based on 5th edition.
Thanks
Nabs
Wed, 05/14/2014 - 11:59
Permalink
will there be difference in
will there be difference in answers if answered from 4th or 5th Ed?
Please give your opinion on this question based on 5th edition.
Thanks
kumarks984
Tue, 05/13/2014 - 15:06
Permalink
As per PMBOK 5th edition, the
As per PMBOK 5th edition, the answer should be clearly B since Stakeholder Analysis is a T&T of Identify Stakeholders which is done in Initiation of the project.
Sundara.damaraj...
Tue, 05/13/2014 - 15:47
Permalink
As per PMBOK 5th edition, the
Option B is "When developing the project charter".
You are saying stake holder analysis is done during Initiation of the project. But there is no such option given.
****
I agree with you Stake holder analysis is done in Identify stake holders(Initiation), since the option is not given.
The next best option is "C" ie When creating the project management plan.
Coz, in develop project mgmt. plan process,
the PM plan is updated for "requirements and techniques for communication among stakeholders".
I agree with others this question is not framed correctly.
kumarks984
Tue, 05/13/2014 - 19:55
Permalink
Stakeholder Analysis gives
Stakeholder Analysis gives you a list of who need to be taken into consideration throughout the project which is preparing "Stakeholder List", an output result as part of "Develop Project Charter" - Reference: Page 72 PMBOK 5th ed.
sunku65
Wed, 05/14/2014 - 12:30
Permalink
Identifying stakeholders
Identifying stakeholders process is initiating to closing.
In some special case, more stakeholders found in except initiation.
What about this stakeholders analysis is not going to consider or not?
Where you going to considering it?
Sundara.damaraj...
Wed, 05/14/2014 - 13:18
Permalink
Identifying stakeholders
Correction- Identify stakeholder process is not till closure.
Identify stakeholder process is only during Project initiation. This creates stakeholder register first time.
However, for any stakeholder addition,deletion,modification will happen till M&C.
Stake holder register is a project document, which contains upto date list of stakeholders.
Stake holder register is an output of
1) Plan stakeholder Management
2) Manage stakeholder engagement
3) Control stakeholder engagement.
Hope this clarifies.
The bottomline is "Identify stakeholder" process is in Intiation Process group only.
sunku65
Wed, 05/14/2014 - 14:14
Permalink
In response to your above
Sundara.damaraj...
Wed, 05/14/2014 - 15:35
Permalink
In response to your above
Its B
sunku65
Wed, 05/14/2014 - 15:41
Permalink
In above post mentioned that
In above post mentioned that Identifying stakeholders except initiation.
That means already Project Charter is created.
sunku65
Wed, 05/14/2014 - 15:49
Permalink
NO Analysis only high level information in Project Charter