Change control Question
Submitted by Nabs on Mon, 05/12/2014 - 07:37
Which of the following BEST describes the procedure by which the project schedule can change, and includes the paperwork, tracking systems, and approval levels necessary for authorizing changes?
A) Configuration management system
B) Schedule comparison bar charts
C) Schedule change control system
D) Integrated change control
Correct answer is C. can anyone explain why it is the correct choice. I couldn't find “Schedule change control system ” in PMBOK.
Forums:
admin
Mon, 05/12/2014 - 16:44
Permalink
Its an old term, probably not
Its an old term, probably not in PMBoK 5. You can read about that here. http://www.itpmpro.com/2008/03/what-is-schedule-change-control-system.html
Nabs
Wed, 05/14/2014 - 11:45
Permalink
Thank you.
Is it possible that these type of terms from old version of PMBOK appear in exam. i am planning to appear in exam next month.
sunku65
Wed, 05/14/2014 - 13:05
Permalink
NO, Not at all. Its purley
NO, Not at all. Its purley from PMBOK5.
Don't study very very old versions from Pages.Google. Study only relates to PMBOK5.