PLEASE LET ME KNOW THE SOURCE OF THE QUES

What is a recommended method for controlling change within a project?
a.
Have only the project manager able to initiate change
b.
Have each change approved or rejected by a board
c.
Allow each project member ultimate control of changes within their realm of the project without a review process
d.
Freeze scope and allow absolutely no changes

2. The project manager of a project calls you in as a consultant to provide inputs on developing the Project Charter. Your contribution to the project could be best termed as:
a.
Professional Consultant
b.
Expert Judgment
c.
Charter Consultant
d.
Expert Consultancy

3. Which process is concerned with providing forecasts to update current cost information?
a.
Monitor and Control Project Work
b.
Project Management Information System
c.
Close Project or Phase
d.
Direct and Manage Project Execution

4. Which of the following would not be considered as an Enterprise Environmental Factor during the Develop Project Charter process?
a.
Scope Statement
b.
Organizational infrastructure
c.
Governmental standards
d.
Marketplace conditions

1. B (Change control Board)
2. B (its part of TT for project charter)
3. A (This is where you measure your costs and is the output of control Costs)
4. A (The statement is an output during the planning process and is part of the define scope)

cheers

Thanks a lot. Which Test Bank. like I am planning to consider for diff book or online to practice the quiz. so this questions got from where ?Do you know Please ..