dispute with seller
You are a project manager and having dispute with your seller over certain changes. The seller claims it's a change request and you think it as a requirement of the product. The seller has formally disputed this. You have met once to discuss the dispute but no agreement could be reached. What should be the best way to resolve this?
A)Take this case to ADR (Alternative Dispute Resolution Team)
B)Continue to negotiate for few meetings and try to resilve the dispute
C) Involve the sponsor to settle this claim
D)Cancel the contract, as it is something wrong the seller is talking about


sanskrit
Fri, 05/31/2013 - 11:56
Permalink
A ?
Option A ?
vijayavadrevu
Fri, 05/31/2013 - 12:45
Permalink
I too have answered as option
I too have answered as option A, looking at the sentence, " You have met once to discuss the dispute but no agreement could be reached"
Whereas the answer is given as option B
ColettaRuiz
Tue, 03/11/2014 - 02:46
Permalink
I'm also considering this
I'm also considering this option A. If its in my case, I'll ask for writing help regarding the transcriptions.
Jgrind07
Fri, 05/31/2013 - 14:44
Permalink
Best way to settle disputes
Best way to settle disputes is Negotiation. PM tried the negotoation only once. So he has to try again for Negotion. He can go to ADR if contineous Negotiatoins are failed. Hence the option B is correct.
Thanks
Jai
cnppmp
Fri, 05/31/2013 - 14:50
Permalink
Disputed claim should be dealt by ADR
It has been formally disputed by seller, so it should be dealt by ADR.
No where it is mentioned as per the contract to cancel the contract or taking any such drastic action.. Since it ahs been formally disputed there is no chance of further negotiating at PM level. I do not think it is Spnosr responsibility, may be procurement manager would have in case mentioned in different context.
Regards
CN Patil
ColettaRuiz
Tue, 08/13/2013 - 08:21
Permalink
I've disclosed such scenario
I've disclosed such scenario to some paper discovery expert from California and their best suggestion is option A. That could make business more professional.
antonyvd
Tue, 08/13/2013 - 08:31
Permalink
Dispute with seller
Negotiation is the best way to settle claims with seller.Since the buyer has met only once with seller,he can make more negotiation to bring him to a amicable settlement.If the negotiation is fruitless,then he can go for ADR.So I think the best option is 'B'- Continue to negotiate for few meetings and try to resolve the dispute.
pmbrett
Tue, 08/13/2013 - 17:19
Permalink
1) negotiation2) if that
1) negotiation
2) if that fails, then ADR
3) if that fails, then litigation
-brett, PMP/Professional Contract Manager
GSA
Mon, 08/26/2013 - 05:49
Permalink
Re-negotiation
I also think B is correct. The seller has formally disputed after the misunderstanding occurred. They have just met once so I think, re-negotiation is a better option. I believe that PM should try as much as he/she could to negotiate before going to ADR and litigation.
So, for this situation:
1. Negotiate
2. Re-negotiate
3. ADR
4. Litigation
Thanks.
kmohan
Mon, 08/26/2013 - 07:37
Permalink
Firstly, it depends on the
Firstly, it depends on the contract terms and conditions on what action has to be taken. So, the buyer may to have to refer it. Secondly, here the seller has "formally" disputed. This means that he must have sent a legal notice. If that is the case, then the option is to take it to ADR. As the buyer/seller already met once and no agreement could be reached, the buyer also has to reply formally. Negotiations are usually out of the court settlements and hence I think the answer should be A.
karanmehta
Wed, 09/18/2013 - 07:42
Permalink
Answer A
The answer is A...PMBok 5 mentions this (pg: 384):
If the parties themselves do not resolve a claim, it may have to be handled in accordance with alternative dispute resolution (ADR) typically following procedures established in the contract. Settlement of all claims and disputes through negotiation is the preferred method.
kevinkkyip
Tue, 03/11/2014 - 04:17
Permalink
I agreed that 'A' is the best
I agreed that 'A' is the best option. As the Seller FORMALLY disputes it, the PM should also deal with it with ADR. Being said that, it does not bar the negotiation to continue in parallel. If that succeeds, the ADR can be dissolved.