Question
Submitted by Judy on Sun, 07/28/2013 - 01:14
I'm stuck
On Anne's project, the Budget at Completion (BAC) is $260,000: Earned Value (EV) is $75000 and Actual Cost (AC) is $68,000. Based on this the percent complete is_______________ and the percent spent is _______________.
a) 40%, 60%
b) 91%, 29%
c) 29%, 26%
d) 26%, 29%
Forums:


pmpnewster
Sun, 07/28/2013 - 01:42
Permalink
Ans: C
Ans: C
% complete = EV/BAC = (75000/260000)* 100 = 28.85 ~ 29
% spent = AC/BAC = (68000/260000)* 100 = 26.15 ~ 26
What's the official answer, pls?
Thanks.
Regards.
Judy
Sun, 07/28/2013 - 02:27
Permalink
c is the answer. thank you
c is the answer. thank you for your response