Nice Question
Submitted by elthox on Thu, 07/18/2013 - 11:51
You are employed by a company that provides project management services to technology organizations. Your company is trying to land a contract with the U.S. Federal government, which would be a significant boost to your company's profile and profits. You are working on the team that is preparing a formal bid for the work. Which project management process are you engaged in?
Forums:


cnppmp1
Thu, 07/18/2013 - 12:10
Permalink
C
Conduct Procurement, as Bidding is part of the Conduct Procurements. Secondly, in this context you as manager is from Seller organization not from buyer and you are preparing for bid is conduct procurement. is that right?
Regards
CN patil
pmpnewster
Thu, 07/18/2013 - 13:36
Permalink
C. Conduct Procurements
C. Conduct Procurements should be the answer, I feel.
Regards.
vikula01
Thu, 07/18/2013 - 18:16
Permalink
answer A
If I am the project manager from seller - I am working on a bid to get the project from FBI --so I don't have a project to work on yet -
Option B is not a process
Option C would have been right if I were a FBI PM
Option D is not correct because we are dealing with contract
pmpnewster
Thu, 07/18/2013 - 19:12
Permalink
Hi elthox,Can you pls post
Hi elthox,
Can you pls post the official answer / explanation?
Thanks.
Regards.
elthox
Thu, 07/18/2013 - 19:21
Permalink
Expanation from
Explanation from Velociteach;
Answer C is correct, though it is not intuitive; you are actually participating in the Procurement Management process called Conduct Procurements. It is a process executed as part of the government's project. Bids and proposals are inputs to this process, and that is what you are preparing.