Last Activity in closure

 Q. Which of the following is the last activity to perform while closing a project..?

 
A. Creating lessons learned
B. Releasing resources assigned to the project
C. Verify Scope
D. Close procurements
 
 
If possible , can someone share a closing sequence of cases with/out procurement..?

 C - D - A - B

 Some mock test answers says that  close procurement is the last activity,which I couldn't agree with.

 

Many thanks for your confirmation.

 Close procurement needs to happen before close project can happen which means that close project activities needs to finish last and the sequence written by first person on this chain is the correct sequence according to me as well. 

cnppmp1's picture

B

 

Regards

CN Patil

verify scope is M&C process
Close procurements is before Close project
For LL you need the team
So releasing team is last