Costs
Submitted by elthox on Sat, 07/13/2013 - 18:25
| You note that the ability to influence the cost of a project is: |
||
| Choice 1 | Greatest at the early stages of the project | |
| Choice 2 | Greatest at the middle of the project | |
| Choice 3 | Greatest at the project closure stage | |
| Choice 4 | Constant throughout the project | |
Forums:


humanbeing2001
Sun, 07/14/2013 - 05:47
Permalink
option 1
option 1
elthox
Sun, 07/14/2013 - 11:40
Permalink
Lets take in consideration
Lets take in consideration two options;
If there is a scope change near closure or at beginning, where the cost are influenced more? At beginning or closure?
humanbeing2001
Tue, 07/16/2013 - 18:36
Permalink
Reread the question with
Reread the question with ability.