What comes after initial Project Schedule and Budget ?
Submitted by rjbuzzing on Wed, 07/03/2013 - 22:07
The project team has just completed the initial project schedule and budget. The NEXT thing to do is:
A. Identify risks.
B. Begin iterations.
C. Determine communications requirements.
D. Create a bar (Gantt) chart.
Please explain your answer.
Forums:


humanbeing2001
Thu, 07/04/2013 - 05:59
Permalink
Option C
During Planning Process, Determination Communication Requirements as a part of Plan Communications Management happens after intial project Schedule & Budget.
Please correct me me If I am wrong.