Risk Register is an output of ?
Submitted by rjbuzzing on Mon, 07/01/2013 - 20:19
Risk Register is an output of ?
1. Plan Risk Management
2. Identify Risks
3. Develop Project Plan
4. Develop Project Charter
PS: Head First Book mentioned it incorrectly.
Do we identify high level risks in the begining - in PM Plan or Proj. Charter ? and does that finally outputs Risk Register or those high level risks are only mentioned in bullets in the Charter or Plan ?
Forums:


humanbeing2001
Tue, 07/02/2013 - 10:04
Permalink
Identify Risks. Option 2.
Identify Risks. Option 2.