Submitted by vijayavadrevu on Tue, 06/04/2013 - 15:38
A major construction project has included in the project budget the cost of the construction loans taken out to finance the work, and this will be accounted for on a monthly basis. The project manager will factor in these cost estimates into the project during which process?
Forums:


MANOJ RAMRAOJI ...
Wed, 06/05/2013 - 04:29
Permalink
Activity Duration Estimates
R3HAB2
Tue, 06/04/2013 - 16:14
Permalink
DETERMINE BUDGET PROCESS
I vote Determine Budget process since these cost estimates have already been created and will serve as inputs into the budget.
Sincerely,
R3HAB2, PE