delivery dates

  Delivery dates and availability of resources can be found in the __________detail.

A) WBS

B)SOW

C)Project Charter

D)Project Scope Statement

Delivery dates and availability of resources are constraints. Constrains are part of project scope statement.

Answer is D

Out of given options SOW and PC is obviously NOT. It could be WBS dictionary and not WBS.

Product description, project deliverables, Acceptance criteria, exclusion, assumption and constraints (TCS) are the part of Prj. Scope statement. Hence the ANS is D

 

Reagards!

Manoj

Answer is given as WBS. May be WBS detail can be taken as WBS dictionary. 

@Manoj

I think the WBS dictionary in the Glossary of PMBOK is stating that it can include details of "Delivery dates and availability of resources"

Was this what you were referring to?

cnppmp's picture

WBS


Regards


CN Patil