response to opportunities
Submitted by Fariba on Fri, 05/31/2013 - 00:26
In your project, which of the following strategies would you not use as a response to opportunities?
Choice 1 Exploit
Choice 2 Contingent
Choice 3 Share
Choice 4 Accept
Forums:


sandeshkd
Fri, 05/31/2013 - 08:19
Permalink
is it 2?
is it 2?
cnppmp
Fri, 05/31/2013 - 08:27
Permalink
4.Accept
Accept, you do not have option to respond..the rest you have because you have to plan for the response but the 'accept' in case of threat or opportunity , nothing can be done than accepting..is that correct?
Regards
CN Patil
vijayavadrevu
Fri, 05/31/2013 - 09:27
Permalink
It shoulde be 2Contingent
It shoulde be 2
Contingent Response Strategies is a tool in Plan Risk Response process. This strategy is applied only if certain event occurs
The question is referring to Opportunities or positive risks for which the strategies are exploit, enhance, share and accept
Vishwanath
Fri, 05/31/2013 - 09:24
Permalink
4
4
Fariba
Sat, 06/01/2013 - 02:01
Permalink
Answer is 4
I answered 2 as well. But pmstudy says is 4 because accept is for both positive and negative risks.
I still do not agree with the answer. Please see page 305 of Pmbok.
cnppmp
Sat, 06/01/2013 - 04:56
Permalink
Understand the question ..
It is mentioning about 'NOT', so there nothing you can do as response for eminent risk occuring and you don't have any strategy than to accept it.
Regards
CN Patil
Fariba
Sat, 06/01/2013 - 10:54
Permalink
Thanks CNPPMP
now I understand. The question is not just asking for four types of positive risk or opportunities.
Thanks again.