Critical Path Question
Q1: Assuming that the critical path of your project has duration of ten days, which of the following cannot affect the project timelines?
Choice 1 If the project has one critical path, you are able to decrease the duration of the critical path by one day by using a new tool.
Choice 2 If the project has one critical path, you have to increase the duration of the critical path by one day due to delays.
Choice 3 If the project has two critical paths, you are able to decrease the duration of one critical path by one day by using a new tool.
Choice 4 If the project has two critical paths, you have to increase the duration of one critical path by one day due to delays.
Q2: The following provides information on a particular task in your project:
Early Start(ES): 25 days
Late Start(LS): 30 days
Early Finish(EF): 50 days
Late Finish(LF): 55 days
Based on this information, you can deduce that:
Choice 1 The task is on the critical path.
Choice 2 The project may get delayed.
Choice 3 The project float is 5 days.
Choice 4 The task is not on the critical path.
Your choices for thoese questins and justificatin please?
Thanks
Jai


sspawar
Sun, 04/28/2013 - 23:47
Permalink
1 4search old post 1st q has
1
4
search old post 1st q has been asked
Jgrind07
Mon, 04/29/2013 - 03:33
Permalink
Thanks, Pawar.
Thanks, Pawar.
Hemant Tandon
Mon, 04/29/2013 - 00:40
Permalink
Question#1Critical Path: It
Question#1
So, answer is choice#3.
Regards,
Hemant, PMP
Hemant Tandon
Mon, 04/29/2013 - 00:46
Permalink
Question#2Points to
Question#2
Points to remember:-
o
Free Float: This is the amount of time an activity can be delayed, without impacting the early start date of its successor.
o
Total Float or Slack: It is the amount of time that an activity can be delayed without delaying the project’s end date.
o
Project Float: Number of days a project can be delayed without delaying another project.
o
Late Finish - Early Finish
o
Late Start - Early Start
Apply above mentioned information on all the choices:-
So, answer is choice#4.
Regards,
Hemant, PMP
pmpnewster
Mon, 04/29/2013 - 02:41
Permalink
Q1: 3Q2: 4
Q1: 3
Q2: 4
crushPMP
Mon, 04/29/2013 - 02:45
Permalink
Q1. CQ2. D
Q1. C
Q2. D
Jgrind07
Mon, 04/29/2013 - 03:28
Permalink
The correct answers are:Q1.
The correct answers are:
Q1. Option 3 (C)
Q2. Optioin 4(D)
Thanks, Hemant for your detailed explaination.
BTW, these 2 questins are from PM Study mock exam that I took today.
Thanks
Jai