Add a note hereWhich of the following should be done FIRST during the Project Life Cycle?




  1. Add a note hereList the key people and organizations that have a stake in the project.



  2. Add a note hereAscertain the stakeholder interests and expectations for the project.



  3. Add a note hereIdentify the key people and organizations that have a stake in the project.



  4. Add a note hereSelect and quantify the stakeholder interests and expectations for the project.


Scordo PMP Lite Mock Exam 12

 
A. List the key people and organizations that have a stake in the project.
B. Ascertain the stakeholder interests and expectations for the project.
C. Identify the key people and organizations that have a stake in the project. 
D. Select and quantify the stakeholder interests and expectations for the project.
 
We need to Identify first, followed by Listing them, later comes analysis about their expectations and interests for the project.

 

Hi, I'd say C, as you can list only what you have previously identified.
 

I second on C; think this refers to communiation Mgt plan: identify SH in the Initiation process group. U would have to identify, list them (SH Reg) before talking of Analyzing the SH interests (expectations or concerns).

According to me the answer must be option C.