Someone please help me on this network diagram concept:
Submitted by AD on Sun, 03/31/2013 - 18:25
Someone please help me on this network diagram concept:
While developing network diagram HeadFirst book adds 1 day while moving forward from one activity to other
so, ES of B = LS of A + 1. Subtraction happens on backward
Rita assumes ES of B = LS of A.
I always make wrong answer to these questions when it should be an easy catch.
Thanks in advance,
AD
Forums:
pan_ajay
Sun, 03/31/2013 - 18:42
Permalink
Some tricks
Its a most debateble topic.
What I feel PMP exam will give the numbers and then will ask you soemthing on it. I dont think they will give any ambiguos question that has 2 ways of solving it.
Regards,
Ajay
Julbrown31
Wed, 04/03/2013 - 02:52
Permalink
Rita, PMStudy, Villanova
Rita, PMStudy, Villanova materials all use 0
sandeepdel
Mon, 04/01/2013 - 00:23
Permalink
Both the methods
Hi..pmbok 5 has shed some more details on it. I feel first method makes more sense as it matches with how we creates project plan. Can you pls post those questions where you are getting wrong choices. Then we can discuss more on them particularly .
sspawar
Mon, 04/01/2013 - 01:10
Permalink
can
can refer
http://www.pmzilla.com/time-management-questions
er-sspawar.blogspot.in
AD
Mon, 04/01/2013 - 03:57
Permalink
Here is the question
Sample question is question 106 on this link:
http://www.headfirstlabs.com/PMP/free_exam/HeadFirstPMP_PracticePMPExam....
y0zh
Mon, 04/01/2013 - 06:19
Permalink
Which method should we use on
Which method should we use on PMP exam? zero or one day?
sspawar
Mon, 04/01/2013 - 10:07
Permalink
Questioned on mail and my reply
Hello Pawarjee,
I have a question regarding ES EF LS & LF questions
you mentioned in the forum that in exam to follow 0 method.
If there are 2 options for 0 and 1 then to go for 0 method.
I want to know did you get this kind of questions in exam
where both the ans were present that is 0 and 1 method.
Pls let me know.
Thanks
-------------------------
From
S S Pawar <pawarindo@gmail.com>
No, so far not asked Like such.
So Generally you will not find any complexity.
Though in case you find both options without any
Figure 6-18--Added the following clarifying the note to the figure. This example uses the accepted convention of the project starting on day 1 for calculating calendar start and finish dates. There are other accepted conventions that may be used
AD
Mon, 04/01/2013 - 14:27
Permalink
Please answer this question
Please answer question 106 on this link:
http://www.headfirstlabs.com/PMP/free_exam/HeadFirstPMP_PracticePMPExam....
sspawar
Mon, 04/01/2013 - 15:24
Permalink
referhttp://www.pmzilla.com/
refer
http://www.pmzilla.com/headfirst-question
if you are really following many posts based on 0 and 1 start methods/or my blog and then will analyse , q 106, you will not ask it.
AD
Mon, 04/01/2013 - 22:34
Permalink
Thanks for sahring the
Thanks for sahring the discussion and links but I am still not sure what would be the correct answer if this question appears on th exam.
Thanks,