All technical work is completed
Submitted by steelproject2012 on Sat, 01/26/2013 - 16:52
All technical work is completed on the project. Which of the following remains to be done?
A: Verify scope
B: Plan Risk Response
C: Create a staffing management plan
D: Complete lessons learned
What does "all technical work" refers to?
Source: Rita 6th edt
Forums:
rjbuzzing
Sat, 01/26/2013 - 17:05
Permalink
Now A and D both can be
Now A and D both can be correct answers, but i would go with A - Verify Scope as that will the immediate task after the completion of Work. aka. Technical work.
What is the correct answer as per Rita ?
anand2381
Sat, 01/26/2013 - 17:36
Permalink
Its A. Verify Scope
All technical work can mean validated deliverable which will be input to Verify scope.to validate against scope.
sspawar
Sun, 01/27/2013 - 01:52
Permalink
This is also a
This is also a disputed question wrt PMBOK4.
as per clause 5.5.3.1, technical work is part of scope , and not as complete as scope.
PMBOK does not use term technical work , the identical term in PMBOK is technical performance.
better definition is on 11.6.2.4 and alo in glossary.
verify scope is fomalizing acceptance ------5.4.
option A is I think more correct.
--------------
in PMBOK 5 - process VERIFY SCOPE is now replaced by VALIDATE SCOPE
steelproject2012
Sun, 01/27/2013 - 13:49
Permalink
Correct response as agreed
Correct response as agreed (and as provided by Rita) is A: Verify Scope.
The work has been completed; We need customer validating the deliverables(Verify Scope process) before documenting "lessons learned"