Response for Accepted Risk ?
Submitted by rjbuzzing on Mon, 01/21/2013 - 03:32
While monitoring the project you find that an accepted risk is going to occur. Which of the following will you use to develop for the response?
A. Risk Response Plan
B. Fallback Plan
C. Mitigation Plan
D. Risk Register
Forums:


admin
Mon, 01/21/2013 - 04:12
Permalink
Since its an accepted risk,
Since its an accepted risk, there will not be any risk response planned , so you should go with Fallback plan.
Regards
rjbuzzing
Mon, 01/21/2013 - 05:58
Permalink
Sounds Good, Inline with
Sounds Good, Inline with PMBOK.
philzs
Thu, 04/02/2015 - 12:38
Permalink
I saw that question from
I saw that question from another source, the answer was Risk Response plan..
Not too sure now..
Also, why we don't use a contengency reserve, this is what we usually have for accepted risk ( ok answer is not there )
th9063
Mon, 01/21/2013 - 10:07
Permalink
D risk register
D risk register
sspawar
Mon, 01/21/2013 - 12:30
Permalink
Ans would be B as said above.
Ans would be B as said above. Risk Register will not have any information/plan for accepted risk.
MANOJ RAMRAOJI ...
Mon, 01/21/2013 - 15:34
Permalink
Explanation for Option B
Dear,
This question belongs to plan risk responce process. For any accepted risk you will use fall back plan from risk register. The risk register contains the strategies, options and actions etc.
sspawar
Tue, 01/22/2013 - 07:38
Permalink
because most of the fall back
because most of the fall back plan depends on situation developed after or during risk is occuring.
Q is specifically asking what you will use to develop the response.
please give answer what thing risk register will give you?
anand2381
Wed, 01/23/2013 - 05:09
Permalink
Option B as per PMBOK
Fallback plan as per Page: 303