Questiona that need explanation/Justification
Question 1 :
You are managing the changes made to the scope baseline. The causes of variances and the reasoning behind the corrective action chosen should be included in:
Choice 1 Recommended corrective action
Choice 2 Project management plan
Choice 3 Scope management plan
Choice 4 Organizational process assets updates
Question 2:
You are monitoring and recording results of assessing performance and recommending necessary changes. What do you get from this exercise?
Choice 1 Quality control measurements
Choice 2 Quality management plan
Choice 3 Quality metrics
Choice 4 Quality checklists
anand
Mon, 05/17/2010 - 11:34
Permalink
cause of variance n corrective actions
Should be updated in
Organizational process assets updates
anand
Mon, 05/17/2010 - 11:47
Permalink
answer to Q 2
Project Quality Management includes the processes and activities of the performing organization that determine quality policies, objectives, and responsibilities ,
So it should be choice 2
badhrig
Mon, 05/17/2010 - 11:50
Permalink
Anand: Thanks 4 your
Anand: Thanks 4 your replies... please explain/justify your answer... will discuss it and then will give you the correct answers....
BR
Bad...
ChandraR
Mon, 05/17/2010 - 11:52
Permalink
For Q-2 answer is Choice 1
For Q-2 answer is Choice 1. Quality control measurements. Here you are comparing the recorded measurements against the established quality metrics and applying/recommending needed corrections for the deviations. QC measurements or for that matter any performance reports are the output of M&C process
Let us look at process of elimination approach:
You are in M&C process- not in planning process - Choice 2 ELIMINATED
Check lists is not an output of M&C process - Choice 4 Eliminated
Quality Metrics are established in Quality planning process - not in M&C process -Choice 3 eliminated
Chandra
badhrig
Mon, 05/17/2010 - 11:57
Permalink
Thanks Chandra will wait for
Thanks Chandra will wait for others reply and justification/explanation...
BR
Bad...
anand
Mon, 05/17/2010 - 12:03
Permalink
Q 2
Chandra I am ok with what you have stated .
But when i see this "What do you get from this exercise? " , I would say its Choice 2 Quality management plan.
and i need to update my quality management plan with the recorded changes.
This is my assumtions looking at the scenario,may be what Chandra said may also stand true.
Badhri has to tell us the answer and only then we can discuss/close
ChandraR
Mon, 05/17/2010 - 12:17
Permalink
Anand, In general, M&C and
Anand,
In general, M&C and Execution go back & forth until the deliverables meet the specifications laid out in the Project Management Plan.
Chandra
ChandraR
Mon, 05/17/2010 - 12:03
Permalink
For Q-1, answer is Choice 1 -
For Q-1, answer is Choice 1 - Recommended Corrective action.
In our organization we call it as CAR (Corrective Action Report). The template we use consists of 3 subtitles
Problem Statement & Expected measurements/specifications
Actual Measurements
Corrective Actions/Recommendations
Let us look at why the other choices do not make as much sense:
Project Management Plan - A generic approach and overview of how the project should be carried out, what are the guidelines to address all possible scenarios etc- Not a detail for Specific situations, approaches, solutions etc
Scope Management Plan- Details what is covered and what is not covered for the project deliverables - Again not a location for CARs etc
OPA: A location for LLs, knowledge base, Infrastructure and resources available and acquired etc - Again not a location for specific CARs, problem solving techniques used
Chandra
badhrig
Mon, 05/17/2010 - 12:24
Permalink
Lets forget about the answers
Lets forget about the answers just for now....
For Q1: Anand: forget about what your organizatoin is doing(PMI does not recomend this point of view, and no hard feelings when I say that) I do accept you approach but is it right or what is right is the question??
Option1: Recommened corrective action is part of the Integrated change control process, the scenario here is there is a change to the scope baseline so need to think from that angele....
Option 2: Project management plan, this can be one of the answers but need to wait for others justification/explanation
Option 3: Scope Management plan, Again this can be one of the answers...
Option 4: Organization process asset updates, this can again be potentially an asnwer, as you are making changes to the scope baseline, you already have some records in the current projects organizationl process asset. again will wait for others
For Q2: I can go with chandra if this is going to be based on the elimanation process explaind by him, others explanation/justificatoin and/or interpretation are also welcome to get a clear picture of the questoin....
BR
Bad...
ambahnaresh
Mon, 05/17/2010 - 14:13
Permalink
For Question # 1 :- Since
For Question # 1 :- Since change has already been made to scope base line, so you would have to update scope base line management plan( This is the subset of Project management plan )...so correct answer would be Project management plan
For question # 2:-
Quality Management Plan, Quality Matrix and Checklist are output of Plan quality process..since you are in Quality m&C process so correct answer is Quality control measurements
badhrig
Mon, 05/17/2010 - 17:59
Permalink
Is any1 posting a
Is any1 posting a responce/explanation ??? or shaill I post the answers ??Please reply...
ambahnaresh
Mon, 05/17/2010 - 18:30
Permalink
Answer pls
Answer pls
Kitu
Mon, 05/17/2010 - 21:16
Permalink
In my opinion Q1) Ans: OPA We
In my opinion
Q1) Ans: OPA
We are in the control scope process here and OPA should be updated (An o/p of control scope) with the causes for variance, corrective action chosen and LL
q2) Ans: QC measurements
This process refers to monitoring and control and so this seems the most logical o/p.
pradeepsodha
Tue, 05/18/2010 - 05:44
Permalink
Questiona that need explanation/Justification
Q-1 I will go with option 4. The question says you are managing changes....the causes and all other details shall be included in OPA go retrive it whenever required.
Q2 I will go with option 1. The process is Perform Quality control and output is Quality control measurements.
Pradeep
badhrig
Tue, 05/18/2010 - 06:41
Permalink
This is the answer and
This is the answer and justificatoin given by the website...
If some1 can explain/interpret it that would be nice...
Q1:
Correct Choice : 4
Justification :
Organizational process assets updates: Organizational process assets that may be updated include, but are not limited to, causes of variances, corrective action chosen and the reasons, and other types of lessons learned from project scope control
Q2:
Correct Choice : 1
Justification :
Quality management plan is an output from Plan Quality process and quality metrics. Quality checklists are the inputs to Perform Quality Control process.