which project to select
Submitted by sunitaPMP on Wed, 01/30/2013 - 00:48
came across this question.
Which project should you selet?
a) project A with oppertunity cost $100,000
b)Project B with Benefit cost ratioof 0.75
c)Project C with IRR of -2%
d)Proj D with NPV of $100,000
Forums:


admin
Wed, 01/30/2013 - 05:40
Permalink
Similar question was just
Similar question was just discussed, search the forum
sunitaPMP
Wed, 01/30/2013 - 06:29
Permalink
am not finding it.So what is
am not finding it.So what is the search string for this question?
peeyushm
Wed, 01/30/2013 - 09:09
Permalink
Here is similar
Here is similar discussion: http://www.pmzilla.com/need-your-inputs-0
Ans of this Q should be D
b) and c) are not favorabel condition
a) not sure about worth of this project
d) NPV = income-cost = $100K +ve, which is good for investment.
Hence ans id D)
sunitaPMP
Wed, 01/30/2013 - 18:30
Permalink
Hello SSPAWR ,Can you please
Hello SSPAWR ,
Can you please explain answer for this?
Thanks,
nitinhamir5
Wed, 01/30/2013 - 18:35
Permalink
Explanation
a) In this option, if you choose the project you are missing a opportunity of $100k gain from other project.
b) Benefit to cost ratio is .75, means less benefits than the amount we are spending.
c) IRR is -ve , that is rate of return from project is -ve.
d) NPV is $100k , which is best option for obvious reasons.
Thanks
Nitin
sspawar
Thu, 01/31/2013 - 01:24
Permalink
Option D is the
Option D is the answer.
option b and c are nonprofitable.
option A has a opportunity cost , does not reveal any profit.
NPV = 100K means this is the net saving.