When a negative risk occurs in a project, a response to it would be called
Submitted by agoyal2 on Mon, 12/24/2012 - 20:30
The below question is from Christopher Scordo book. I selected the answer as A since there is nothing in the question that indicates that the risk was not planned. The book however mentions that the correct answer will be 'C'.
Your thoughts?
When a negative risk occurs in a project, a response to it would be called:
|
Forums:
sspawar
Tue, 12/25/2012 - 01:52
Permalink
you might be correct
you might be correct but the lesson/ learning from this question is:
Risk responses are always pro-actions/advance actions, and when responses are there, risks will not occur but are nuteralized.
In other word Author's concept is that if risk occurs , means any response plan was not planned and developed in that ratio.
Develop Risk Response means not only an advance planning but an advance action /strategy like - insurance, contract, reserve resources etc.
duongnt
Tue, 12/25/2012 - 06:14
Permalink
C is correct.U should
C is correct.
U should remember that negative risk is not planned at planning stage. A workaround is response for that
shiva_rk
Thu, 12/27/2012 - 10:54
Permalink
Workaround defination under Glossary
C is correct.
As per defination of Workaround under Glossary section, it is a response to negative risk that has occured, as it is not planned in advance.
mpavas
Thu, 12/27/2012 - 12:54
Permalink
perfect answer..as per the
perfect answer..as per the books