What is your choice? I am disagree of the answer.
1. Your organization manages software testing projects and is well known for completing the projects within constraints and as per the project objectives. As an external vendor, you are managing a complex software project that has been contracted on Time & Material (T&M).
One of your team- members reports a break-through in automating some of the testing activities. This will potentially result in cost savings to the project as well as the project getting completed ahead of schedule by a month.
Which of the following actions would you take?
Select one:
A. This is confidential information within your project team and need not be shared with the customer. The savings will be additional profits on the project.
B. Communicate the current status and inform the customer that you will be incorporating some additional features to use up the savings in cost and time since it has been budgeted for.
C. Communicate the current status to the customer and indicate the potential changes to cost and schedule.
D. Communicate the savings in cost and time to the customer. At the end of the project, notify your billing department that they need to prepare an invoice for 50% of the cost being saved.
C is the answer, but why not B? B seem the best answer rather than C.


sunku65
Wed, 05/07/2014 - 08:36
Permalink
B is Gold Plating as adding
B is Gold Plating as adding additional features its not acceptable PMBOK.
C. is correct read Professional & Social Responsibility.
D. Communicating to customer is good but not updating baselines.