What do you think on this QS ?
Submitted by ranatungawk on Sun, 03/02/2014 - 14:37
You know that BAC = 500, PV = 325, AC = 275, and EV = 250 and that you are experiencing typical variances.
What is EAC?
a. 500
b. 250
c. 549.45
d. 525
Forums:


abhinavpraneet
Tue, 03/04/2014 - 07:00
Permalink
The given answer C seems a little off!
Since the question mentions typical variances, it would mean that the EAC would be based on CPI, and not adhere to the original plan. Hence the formula I would go with is EAC=(BAC/CPI).
Therefore EAC=(500/(EV/AC))=(500/(250/275))=550. Answer C is closest, but not the same, which should not be the case in this calculation as it does not have decimals (which can be rounded off).
Abhinav Praneet, PMP
interservicio
Wed, 03/05/2014 - 14:48
Permalink
Answer C.For calculations it
Answer C.
For calculations it is best to calculate three decimals, and round them to two.
Then CPI = 250 / 275 = 0,909 --> 0,91
ranatungawk
Wed, 03/05/2014 - 16:10
Permalink
?????????
According to the Rita's book and sevaral other sources :
1. If no variances from the BAC --- > BAC/CPI
2. If variances is Atypical ---> AC + (BAC-EV)
3. IF variances is Typical ---> AC+(BAC-EV)/CPI
I think, the 2nd formula should be selected for this ,,,, correct ?
interservicio
Thu, 03/06/2014 - 08:39
Permalink
Well not exactly.IF cost
Well not exactly.
IF cost variances had occurred and you expect to keep occurring on the same trend in the future, you have tu use:
EAC = BAC / CPI
If variances occured BUT you don't expect to keep on the futre, you use your second formula EAC = AC + (BAC - EV)
As for the third formula, I think you're referring to this one: EAC = AC + [(BAC - EV) / (SPI*CPI)] which is used for variances to keep on the future and the time constraint is expected to influence the completion of the remaining effort.
To be honest i don't understand 100% the last one, nor i have been seen it in ANY exercise.
philstinnet
Thu, 05/01/2014 - 14:51
Permalink
The last formula is the same
The last formula is the same as the first formula.
EAC = AC + (BAC - EV) / CPI
When you multiply CPI to AC, it will become EV. This EV will cancel out the EV on the right. The net remaining will be BAC/CPI which is the first formula.
Thanks