What is the BEST way to make an accurate forecasting of ETC?

What is the BEST way to make an accurate forecasting of ETC?

A. EAC - AC

B. BAC - EV

C. Manual Forecasting of cost of remaining work.

D. (BAC - EV)/CPI

 

Thanks

Jai

OPTION A

Estimate To Complete = Estimate At Completion - Actual Cost

 somewhere it is askd , in different way.

it is based on line P 184

The most common EAC forecasting approach is a manual, bottom-up summation.

 

crushPMP's picture

Definitely C