Typically signing of project charter is the responsibilty of? PreparePM.com Mock Exam 1 question
Submitted by PMPBOY on Sat, 01/01/2011 - 02:30
Choices given are:
A. Project Sponsor
B. Senior Management
C. Project Manager
D. Project Stake-holders
Among the BOLD ones (C and D are incorrect anyway so), which one is correct? I selected A but answer says Senior Management.
Any thoughts, comments, reasoning please...!
Forums:


admin
Sat, 01/01/2011 - 05:51
Permalink
As per PMBoK 4th
As per PMBoK 4th edition
Projects are authorized by someone external to the project such as a sponsor, PMO or portfolio steering committee. The project initiator or sponsor should be at a level that is appropriate to funding the project. They will either create the project charter or delegate that duty to the project manager. The initiator’s signature on the charter authorizes the project.
PM / Sr Management are co-signers, sponsor signature authorizes the project. Keep the concepts clear, dont worry about the right answers, especially if they are not from reputed sources
Regards,
Admin
urskah
Wed, 01/05/2011 - 22:41
Permalink
I had equal dilemma with same
I had equal dilemma with same question as PMPBOY.
Another question where I think the answer is wrong is also:
Which of the following is not an input to the Conduct Procurements process?
I picked b, but according to preparepm.com it should be d (argumentation: WBS is not an input to the Conduct Procurements process). My argumentation for b is, that make-or-buy analysis can't be input for conduct procurements, because when you are in Conduct procurements, you already decided whether to make or to buy (this is an input in Plan procurements). Am I right?
PMPBOY
Thu, 01/06/2011 - 01:42
Permalink
urskah 4 question of Conduct Procurement Process, they r right.
I am afraid you are not right.
Please refer to page: 329 of PMBOK 4th Edition, and you will see that preparepm.com is RIGHT that WBS is NOT an input to the Conduct Procurement Process.
urskah
Thu, 01/06/2011 - 22:02
Permalink
Huh, I was sloppy...Now, when
Huh, I was sloppy...Now, when I really checked, make or buy is input into Conduct procurements.
KR, U