Timeline change

There are some dependency task cause the delay for the project. The summary timeline is Project charter is 30th September. But the dependancy task only can completed end of the year.

Am I only need to change the Project Management Plan or I need to change the Project charter as well as the deadline definately going to be affected.

admin's picture

 Only Project Plan. Charter's is to authorize the project