Time management Question
Submitted by riyaz145 on Mon, 01/07/2013 - 11:40
An activity has an early start of day 3, early finish of day 9 and late start of day 13 and late finish of day 19. what is the duration of the activity?
1. 3
2. 6
3. 7
4. 10
Need clarification on the answer. Thanks in advance
Regards,
Riyaz
Forums:


madunix (not verified)
Mon, 01/07/2013 - 15:58
Permalink
Activity Duration = EF -ES +
Activity Duration = EF -ES + 1 or LF- LS + 1
AD=9-3+1=7
or
AD=19-13+1=7
riyaz145
Mon, 01/07/2013 - 17:00
Permalink
As per rita
and Pmbok the first day is 0th day then shouldn't it be 6 ?
I was wondering that there's some thing that i'm missing in the Q?
Kindly clarify..
sspawar
Mon, 01/07/2013 - 17:59
Permalink
see below one
see below one
smartcode
Mon, 01/07/2013 - 17:49
Permalink
I think 6 we dont add 1
I think 6 we dont add 1
sspawar
Mon, 01/07/2013 - 17:58
Permalink
Riyaz, you should refer
Riyaz, you should refer old
Riyaz,
you should refer old posts, I have explained this question in ear;ier posts.
you can go to my blog http://er-sspawar.blogspot.in/2012/12/examples-of-network-start-with-0-and.html
then http://er-sspawar.blogspot.in/2012/12/pmi-says-pdm-start-with-zero.html
or for all posts - http://er-sspawar.blogspot.in
--------------------------------------
you are asking many good questions, i could not reply on all.
but if you refer the old posts you will get old discussions. -- just put your query in search box.