Time Management

 

Hi,

Would some explain 'Independent Float' of an activity with an example? I understood that it is the outcome of (FF-tail slack), But conceptwise, I have a gap on this part, like at what situations a PM take advantage of this.

 

 

 

 

 

admin's picture

Check this post 

http://pmzilla.com/critical-path-calculation-network-diagram 

Distinguish between free float and independent float 

Free float: Free float is present if an activity is started at Earliest possible starting time but it can be finished before Earliest finishing time. (FF = EF – ES – time required for activity.)

Independent float: Independent float is present if an activity is started at Latest starting time but it can be finished before Earliest finishing time. (IF = EF – LS – time required for activity)
 
 